Wrapping Up at Faneuil

We Have been very busy over at Faneuil this holiday season. The H-Bay and F-Bay are now complete and the clients have moved in. In the G-Bay, the concrete floor grind and seal is finished. We are currently installing restroom wall tile, hanging and taping drywall throughout and, Next up, we will be painting followed by installation of T-Bar in the training rooms and corridor.

1.11 Faneuil H bay 11.20.2018.jpg
Previous
Previous

Keep an Eye out for Creekside in Downtown Roseville

Next
Next

Nearing the Finish Line at Stanford Ranch