We Have been very busy over at Faneuil this holiday season. The H-Bay and F-Bay are now complete and the clients have moved in. In the G-Bay, the concrete floor grind and seal is finished. We are currently installing restroom wall tile, hanging and taping drywall throughout and, Next up, we will be painting followed by installation of T-Bar in the training rooms and corridor.